Hong Kong - Zhuhai - Macau bridge 

The Hong Kong – Zhuhai – Macau bridge (HZMB) fixed link project provides for a fixed link between the two Chinese economic centres Hong Kong and Macau (both of which are Special Administrative Regions within PR China) and the mainland of China at Zhuhai.
bird eye of HZMB tunnel

© HZMB Authority

Project facts Hong Kong - Zhuhai - Macau bridge

  • Client
    HZMB Advanced Work Coordination Group/HZMB Authority
  • In co-operation with
     TY Lin International; Shanghai Municipal Engineering Design Institute, TY Lin International, Guangzhou Metro Design Institute
  • Country
    China
  • Duration
    2009-2018
  • Location 
    Zhuhai 
  • Project phase
    Feasibility study, Conceptual design, Preliminary & detailed design and Construction phase

Project description

The Hong Kong – Zhuhai – Macau bridge (HZMB) fixed link project provides for a fixed link between the two Chinese economic centres Hong Kong and Macau (both of which are Special Administrative Regions within PR China) and the mainland of China at Zhuhai. The whole link, which measures some 50 km in length, has been divided into several major sections. The Main Bridge section has a length of approximately 30 km and includes a 6 km immersed tunnel that is flanked by 2 artificial islands to accommodate the transition to the bridge part that run towards Hong Kong and Macau / Zhuhai. The Link will carry a three-lane dual carriageway with a design speed of 100 km/h and is designed for a 120 year design life. To accommodate the passing of 300,000 tonnes vessels, the tunnel will be approximately 40 m below the seabed.

Scope of work

Some of the key issues of the HZMB Main Bridge tunnel and island include:

  • Review of preliminary, final design to confirm before entering the tender and procurement stage
  • Review of detailed design and consultancy during construction phase
  • CPT-U special study to introduce in China the use of cone penetration tests as an economic way to explore ground conditions
  • (Detailed) parallel analyses (special studies) to confirm the detailed design on critical issues, such as the longitudinal design including joint design, seismic analyses and cross section structural analyses
Hans de Wit - Managing Director / Senior Consultant

Hansde Wit