Oosterweel bored tunnels for cables

For the expansion and relocation of the existing ring around Antwerp in total 4 bored tunnels for cables and pipelines are constructed to make possible the relocation of the existing highway to below ground level.
Person in bored tunnel

Project description

The bored tunnels have the following specifications:

Location

Groenendaallaan

IJzerlaan

Schijnpoort

Type

single

single

double

Length

175 m

260 m

220 m

Diameter start shaft

15 m

15 m

25 m

Diameter end shaft

10 m

10 m

20 m

Outer diameter tunnel

4,1 m

4,1 m

4,1 m

Top point tunnel

20m below ground level

25m below ground level

25m below ground level

Bottom point shaft

25m below ground level

30m below ground level

30m below ground level

 

Scope of work

TEC parent company Witteveen+Bos is responsible for Civil and Structural works:

  • Preliminary design and final design
  • Structural calculations and drawings
  • Geotechnical calculations
  • Tender documents
  • Cost estimates 
  • Advisory and back office upon construction

 

Project facts

Client
BAM NV
Duration
2014-2015 design 2016-2017 execution
Country
Belgium
Project phase
Completed
Location
Antwerp
Jeroen de Leeuw - Project manager and Specialist bored tunnels

Jeroende Leeuw

Project manager and Specialist bored tunnels