Ningbo

The ChangHong tunnel in Ningbo is crossing the river ChangHong.

Project description

The crossing comprises an immersed tunnel section of 400 m in length of 4 elements each 100 m long. The tunnel width is 22,80 and the overall height is 8,45 m. TEC in association with the Municipality of Rotterdam provided design and supervision services to the Contractor STEC from Shanghai.

 

Scope of work

  • Design support
  • Assistance during construction
 
Cars driving under naviduct

Project facts Ningbo

Client
STEC Shanghai Tunnel Engineering Company
Location
Ningbo
Project phase
Design support and assistance during construction
Country
China
Duration
1999-2002